For the renovation of the new office, the 4th is engineering wiring. Netcom is responsible for the telephone line layout of the entire office, and the network cable is on my head.
The plan adopts a local area network method with the technical department as the starting point, three switches stacked, and multiple routes. It was planned to lay the main line first. The original budget was 200 meters. Unexpectedly, the final result was that 600 meters were not enough.
The three of them worked hard all afternoon and didn't finish work until after 8 p.m.
Looking at the results that I did it but seemed like nothing had been done (all buried in the ground, hidden pipes, smallpox), I still feel a sense of accomplishment.